PRACTICAL GUIDE · PROJECT FINANCE

EU grant co-financing and cash-flow planning

A funding rate does not tell you how much cash you need to deliver a project. Use these examples to distinguish total cost, potential grant, remaining project cost and peak financing needs.

One project, four financing scenarios

All four cases use the same hypothetical €120,000 project: €100,000 eligible expenditure and €20,000 ineligible expenditure. Assume a 50% cost-based grant, capped at €50,000, no revenue, VAT, tax, loan interest or other cash flows. These are illustrative assumptions, not the rules of a real funding call.

ScenarioTotal costGrantNet costPeak cash need
Full reimbursement after costs are paid€120,000€50,000€70,000€120,000
Advance of €20,000 before expenditure; balance after completion€120,000€50,000€70,000€100,000
Cost overrun of €15,000, no increase in grant€135,000€50,000€85,000€135,000
No grant awarded€120,000€0€120,000€120,000

Educational example only. Actual eligibility, funding forms, eligible costs, caps and payment conditions depend on the call and grant agreement. Do not treat the table as an award, financial advice or a forecast.

Three calculations to make

  • Potential grant = lower of the applicable rate × eligible costs and the grant cap (simplified cost-based example).
  • Remaining project cost = total project cost − grant received.
  • Peak financing need = largest cumulative excess of cash payments over receipts, calculated in chronological order.

Why timing matters

For the first case, the company must fund €120,000 before reimbursement and ultimately bears €70,000. In the advance case, €20,000 arrives before spending, reducing the peak requirement to €100,000; the remaining €30,000 arrives after completion. The advance does not change total grant or final net cost. A delay keeps the cash tied up longer and may add financing costs, which are excluded here.

Questions to resolve before applying

  • What costs are eligible, and is the funding amount fixed or recalculated?
  • When may project activities start, and when must costs be paid?
  • Are advances, interim payments or guarantees permitted, and on what terms?
  • Can the business cover the peak need, a delay and a no-grant scenario?
  • Will the project remain commercially worthwhile without the grant?

Read the official call and grant agreement before committing expenditure. Start from the European Commission Funding & Tenders Portal and the guidance of the responsible authority.

Official Funding & Tenders Portal

Assessment methodology · Eligibility checklist

Updated 28 November 2026 · Grantivum